TOP Progress
As at 31 December 2016
RESIDENTIAL DEVELOPMENT
LOCATION
TYPE
TENURE
APPROXIMATE PERCENTAGE COMPLETED(%)
Indicative Status Of TOP* As At 31 December 2016
Vacant Possession Date As Indicated In S&P Agreement
d'Nest
Pasir Ris Grove
Condo
99 years from 20 Oct 2010
92.7
Q3 2017
31 Dec 2017
The Venue
Tai Thong Crescent
Mixed Development
99 years from 5 Dec 2012
91.2
Q2 2017
6 Sep 2017
Coco Palms
Pasir Ris Grove
Condo
99 years from 7 Jan 2008
77
Q2 2018
30 Jun 2019
The Brownstone
Canberra Drive
EC
99 years from 28 Apr 2014
74.2
Q4 2017
28 Jan 2019
The Criterion
Yishun Street 51
EC
99 years from 25 Aug 2014
56.1
Q2 2018
31 Dec 2018
 

* Estimated date subject to changes

Q1: January to March
Q2: April to June
Q3: July to September
Q4: October to December


Next update: 31 March 2017